Before any solar system can be energized, it must clear a crucial milestone: the final inspection. This step—overseen by the local Authority Having Jurisdiction (AHJ)—ensures that the installation aligns with the approved plan set and complies with all safety codes. Passing inspection means your system is safe, code-compliant, and ready for utility Permission to Operate (PTO). Failing it can cost you time, money, and your reputation.
Let’s break down what you need to know—and do—to ace your solar inspections.
Success starts long before the first panel is mounted. A comprehensive plan set—covering site layout, structural attachments, and electrical diagrams—must be submitted and approved. In most jurisdictions, you'll need both building and electrical permits, and possibly utility interconnection approval.
📎 Have these documents ready during inspection:
đź’ˇ Tip: A well-prepared and code-compliant plan set can fast-track AHJ approval and reduce inspection delays.
Inspectors verify that the installed system is exactly what was approved—no surprises allowed. Even small deviations (like adding panels or swapping inverter models) can fail an inspection and require re-permitting.
âś… What inspectors will check:
One of the most critical inspection areas is electrical safety. Your installation must meet the latest National Electrical Code (NEC) and local AHJ requirements.
⚡ Key electrical inspection points:
🛑 Even one missing label or oversized breaker can result in a failed inspection.
The structural integrity of your installation is just as important as its energy output. Inspectors will assess the attachment points, weatherproofing, and fire code compliance.
🏗 Watch for:
Sometimes, inspections reveal unrelated problems. If the property has unpermitted electrical, plumbing, or structural modifications, the inspector is obligated to report them. This can delay the solar project and lead to broader compliance issues.
📣 Advise homeowners to disclose or resolve any unpermitted work before inspection day.
Once installation is complete:
If the system passes, you’ll receive a green tag or written approval. Then, the utility grants Permission To Operate (PTO)—and you can officially power up the system. It’s best practice to walk the homeowner through the monitoring portal and shutoff procedures at this stage.
Before the inspector arrives, double-check the following:
đź”’ Permits & Documentation
🔌 Plan Conformance
⚙️ Electrical System
🏠Roof & Fire Safety
đź“› Labeling
👤 Customer & Site Prep
Treat the inspection as the final phase of the project, not an afterthought. By integrating inspection readiness into your workflow—from the first draft of the plan set to the last roof bolt—you dramatically improve your first-pass success rate.
✔️ Use standardized checklists (like those from SolarAPP+)
✔️ Follow NEC and local AHJ rules to the letter
✔️ Communicate clearly with the customer and inspector
With solid preparation and attention to detail, you’ll get that green tag the first time—keeping your timelines (and customers) happy.
‍